Planned Event - North east core fibre relocation
Scheduled Maintenance Report for Vorco
Completed
The scheduled maintenance has been completed.
Posted Apr 28, 2018 - 10:49 NZST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 28, 2018 - 10:40 NZST
Scheduled
Service(s) Affected: None, hazard notification
Customer Impact: None expected (brief MPLS switching break)
Details: The North East segment of our Auckland core fibre ring needs to be physically relocated due to construction works on the Northern Motorway. During this time services will automatically fail over via West Auckland, but whilst work takes place there is risk due to reduced redundancy.

Actual re-splicing work is expected to take 1 hour during the outage window.
Posted Apr 16, 2018 - 20:57 NZST